Kelderby go-live plan
By Clara Rossi · created 6 Jul 2026, 08:15 UTC · last updated 28 Oct 2026, 10:40 UTC · version 22
kelderbygo-liveplan
Go-live: Monday 2 November, fixed · Owner: Clara Rossi · Account: Ana Ruiz · Kelderby: Priti Shah (IT), Sanne Bech (operations)
Status on Wed 28 Oct: on track. First single sign-on weekend done; second on Sat 31 Oct. Go/no-go on Thu 29 Oct at 15:00.
What goes live
On 2 November all 25 depots start asking for access through ACME instead of Kelderby's forms and emails. Each depot's manager approves their own people in the portal. Head office's two administrators keep All requests.
How people sign in on the day:
- The seven pilot depots sign in with Kelderby's Entra ID (switched on 24 October and 31 October).
- The other 18 depots sign in with passwords until their switch, planned before Christmas with ACM-293.
- Agency drivers sign in with phone codes everywhere.
Workstreams
| # | Workstream | Owner | Status |
|---|---|---|---|
| 1 | Organisation in the EU region | Clara | Done, July |
| 2 | 25 depots created | Clara, Henrik | Done, July |
| 3 | People import (HR export, 2,870 people) | Clara, Priti | Done 5 Oct; dry run 2 Oct |
| 4 | Depot managers as approvers for their depot (ACM-247) | Kelderby's administrators | Done 9 Oct; checked again 27 Oct |
| 5 | Single sign-on, seven pilot depots | Henrik, Clara | Three done 24 Oct; four on 31 Oct. See the rollout plan |
| 6 | Notices by email and in the portal | Clara | Done. EU mail account since 16 Oct |
| 7 | Administrator training | Clara | Done 14 Oct |
| 8 | Depot manager training, 45 minutes each | Clara, Ruth | Tue 27 Oct, Wed 28 Oct, Thu 29 Oct |
| 9 | Phone codes for agency drivers | Clara | Done; drivers tagged in the import |
| 10 | Hypercare, two weeks | Ana, Ines | 2 Nov to 13 Nov |
Go/no-go criteria
Sanne Bech decides with Priti, Ana and Clara on Thu 29 Oct.
- Every depot has a manager set as approver for that depot, and each one has signed in at least once.
- The second weekend's four depots passed their test sign-in in the rehearsal on Thu 29 Oct morning.
- No open SUP ticket from Kelderby at High or above.
- Kelderby's IT line knows the switch-back runbook and who at ACME is on call.
Hypercare
- Daily call at 09:30 with Priti, Ana and Clara, 2 November to 13 November.
- Support watches the
kelderbylabel and answers within the hour on working days. - ACME's on-call engineer covers the weekends. Kelderby calls the support line, not individuals.
Risks
| Risk | What we do | Owner |
|---|---|---|
| A depot manager is on leave and requests wait | No deputies exist in the product. Kelderby's administrators check All requests each morning. Requests close after 14 days, so leave longer than a week needs cover. | Ana, Priti |
| Agency drivers keep access after their shift | Removed by hand after each shift. "One-shift access for agency drivers" is being shaped. | Ana |
| People not in their depot's Entra ID group | Henrik checks group membership against the depot list before each weekend. | Henrik |
| People whose imported email isn't their Entra ID username can't sign in, and new accounts made on the day leave duplicates | Compare import emails with Entra ID UPNs before each weekend and fix the emails first; merge any duplicates. | Clara, Yusuf |
| A driver works at a depot that isn't their home depot | Their request goes to their home depot's manager. Told Kelderby; Lena knows (routing on the requested depot would be a product change). | Ana |
Change history
| Version | Date | Who | What |
|---|---|---|---|
| 1 | 6 Jul | Clara | First plan from the kickoff with Priti |
| 6 | 19 Aug | Ana | Single sign-on over two weekends (ACM-214) |
| 11 | 1 Oct | Clara | Depot approvers live; workstream 4 added |
| 15 | 13 Oct | Ana | Cover while a manager is away; 14-day close |
| 19 | 26 Oct | Clara | First weekend done; duplicates risk added |
| 22 | 28 Oct | Clara | Training dates confirmed; go/no-go criteria |